Steel Erection Insurance: Coverage From the Trailer to the Final Bolt

In short

  • Describe your work by frame type, stories and maximum height, and say so if you sell whole metal buildings or fabricate.
  • Compare your riggers liability limit with the costliest single pick, and match rented crane coverage to the rental agreement.
  • Keep the written concrete notice, any anchor rod notice and your bolting records, because they bear on how a collapse happened.
  • Ask whether an action-over endorsement removes coverage for liability you assume by contract when your own ironworker is hurt.
  • Get the direction to leave perimeter cables, and the controlling contractor’s acceptance of them, in writing before your crew leaves.
  • Read each subcontract for delegated connection design and for any promise to indemnify the engineer, then ask about professional liability.

Follow one beam. On the trailer it is cargo. On your hook it may be somebody else’s property in your hands. Bolted up, it is part of a structure that cannot yet stand alone, and after you leave it is finished work. The exclusion to read can change along the way.

This page is for companies that set frames, joists and deck, put up metal buildings, hoist precast, place rebar, or install stairs and miscellaneous metals. Form wording comes from a sample of ISO form CG 00 01 published by Sonoma County; your form and state law may differ.

What to list on the application

OSHA’s 29 CFR 1926.750 counts “hoisting, laying out, placing, connecting, welding, burning, guying, bracing, bolting, plumbing and rigging” structural steel, joists and metal buildings, along with decking, curtain wall, siding systems, miscellaneous metals and ornamental iron. It leaves out electrical transmission, communication and broadcast towers, and tanks; list those separately.

Then break your receipts down by frame: stories and maximum height, single-story joist and deck, bridges, industrial, precast, rebar, rails and stairs in finished buildings. A company that sells the metal building as a package may also answer for the slab and the panels, depending on its contract. A shop that fabricates has a product too, and exclusion k removes damage to “your product” arising out of it.

While the load is on the hook

Exclusion j(4) takes personal property in the insured’s “care, custody or control” out of general liability, except property damage to premises rented for seven or fewer consecutive days and liability assumed under a sidetrack agreement. A fabricator’s girder, an owner’s rooftop unit or a precast panel can land in that clause when a choker slips, depending on who was directing the pick.

Ask about riggers liability for other people’s property while you lift, move or set it. Compare its limit with the costliest single pick, and check loss of use, loads set down between lifts, and hired cranes. For steel you bought or are paid to install, ask about an installation floater, a form of inland marine.

A bare rental has its own problem: j(1) excludes damage to property you “own, rent, or occupy,” with the same premises exception, which is no use for a crane. Match rented equipment coverage to the value and downtime terms in the rental agreement, and read it for wording on overload and booms.

Section 1926.753 calls for a competent person’s visual inspection of the crane before each shift, rigging inspected by a qualified rigger, and no more than five members in a multiple lift.

Bolted, but not yet a frame

Imagine deck bundles landed on bar joists before the bridging is anchored. The joists roll, a column follows, and the anchor rods tear out of a pier another contractor poured.

Sidetrack agreements aside, exclusion j(5) removes “that particular part of real property” on which you, or contractors or subcontractors working for you, are performing operations, if the damage arises out of them. Exclusion j(6) removes the particular part of any property that must be repaired or replaced because your work “was incorrectly performed on it”; it does not apply within the products-completed operations hazard. Both begin with “that particular part,” which is the argument for coverage of the pier, and the problem for the bay you were setting.

For that bay, look to the project’s builders risk policy. Ask whether subcontractors are insureds, how it treats collapse during erection, temporary bracing and faulty workmanship, and who pays the deductible. Your liability form is excess over other valid and collectible “Builder’s Risk, Installation Risk or similar coverage” for your work available to you.

Keep three papers. You may not erect steel without written notification that the footing, pier or wall concrete (or masonry mortar) has reached 75 percent of its intended minimum design strength, or enough to carry the erection loads. Except on a systems-engineered metal building, anchor rods may not be repaired, replaced or field-modified without approval from the project structural engineer of record, and the controlling contractor must tell you in writing if they were. The third is a bolting record: solid web members other than diagonal bracing stay on the hoisting line until each connection has at least two bolts, and metal building rigid frames need half their bolts or the manufacturer’s number, whichever is greater.

When normal welding precautions are not sufficient, OSHA requires additional personnel to guard against fire, during the work and for a sufficient period after. Ask about hot work conditions.

A rejected weld is not a falling beam

In the Custom Agri decision, an owner said a steel grain bin was defective, and the subcontractor that built it wanted its liability insurer to defend. Answering a certified question in 2012, the Supreme Court of Ohio held that claims of defective construction or workmanship brought by a property owner are not claims for “property damage” caused by an “occurrence” under a policy like that one. One justice dissented, citing Indiana and Texas decisions that treat unintended faulty work as an accident, and one concurred only in the judgment. Opinions the court quoted leave room for consequential damage.

Columns off grid, a doubtful bolt lot or failed ultrasonic tests can hold up the cladding with nothing broken. Exclusion m reaches “impaired property” and property “that has not been physically injured,” if the cause is a defect in your work or “a delay or failure” to perform a contract on its terms. Its exception is for loss of use of other property after “sudden and accidental physical injury” to your work once it has been put to its intended use.

After completion, exclusion l removes damage to your own work arising out of it, unless the damaged work, or the work the damage arises from, was done for you by a subcontractor. If you sub out deck or field welding, check for an endorsement that deletes that exception. A performance bond answers to the other party, and the surety can look to you for repayment.

The second lawsuit after an ironworker falls

Under OSHA’s steel rule, protection is generally required more than 15 feet above a lower level. Connectors must be protected above two stories or 30 feet, whichever is less, and from 15 to 30 feet must have the gear to tie off or other protection. A controlled decking zone is allowed in that band.

Workers’ compensation responds to your injured connector. The connector may also sue the owner and the general contractor, who then turn to the indemnity clause you signed. Exclusion e removes injury to your employees, but “does not apply to liability assumed by the insured under an ‘insured contract,’” and exclusion b makes room for that liability if the injury comes after the contract is executed. An action-over endorsement can take that exception away.

New York’s Labor Law 240 has contractors and owners furnish hoists, stays, slings, braces and other devices for “proper protection” in the erection of a building or structure, except owners of one- and two-family dwellings who do not direct or control the work. Its Workers’ Compensation Law 11 then keeps third parties from recovering contribution or indemnity from the employer unless the injury is one of the listed “grave” ones, death among them, or a written contract made before the accident expressly agreed to it.

Colorado voids a construction clause that makes you indemnify, insure or defend another party against its own negligence, while allowing indemnity up to your share of fault and additional insured status for your acts; contracts that concern railroad property are among those outside it. In construction contracts, Michigan voids indemnity for the sole negligence of the party protected, and a public entity may not require a contractor to indemnify it beyond the degree of fault of the contractor and its subcontractors.

Topped out, cables up, crew gone

Perimeter cables outlast the raising gang. Under 1926.760(e) your fall protection stays for other trades only if the controlling contractor has directed you to leave it and has inspected it and accepted control and responsibility. Washington and California have their own versions. Get the direction and the acceptance signed, floor by floor. A painter hurt on a slack cable may sue whoever strung it.

CG 20 10 covers a scheduled owner or contractor for liability caused at least in part by you, or those acting for you, in your ongoing operations, and another contractor’s use of your deck on the same project does not by itself end it. CG 20 33, the automatic version for a party you agreed in writing to add, ends when your operations for that party are completed. From there the contractor is looking for CG 20 37: liability caused at least in part by your completed work at the scheduled location.

Drawings, delegated connections and the engineer

The military’s guide specification for structural steel, UFGS 05 12 00, offers designers a paragraph requiring an AISC certified erector. It asks for erection drawings showing sequence, shoring and bracing, and has an optional paragraph that delegates connection design, with calculations sealed by a registered professional engineer.

A contractors’ professional exclusion can take design liability out of your policy. CG 20 33 keeps injury or damage from professional engineering services, shop drawings included, out of what the additional insured receives. And the “insured contract” definition leaves out a promise to indemnify an architect or engineer for injury or damage arising from preparing or approving “shop drawings.” Have an attorney read that promise before you sign. Ask whether contractors’ professional liability includes engineers you hire.

One crane, two liability policies

Under the liability form a vehicle kept mainly to carry a permanently mounted power crane is “mobile equipment,” and so is one on crawler treads. If motor vehicle insurance law applies to it where it is licensed or garaged, it becomes an “auto.” Exclusion g then removes injury and damage from its use if an insured owns, operates, rents or borrows it, with an exception for operating the attached machinery. The business auto form mirrors that by excluding operation of such machinery, and it also excludes property moved by a mechanical device not attached to the covered auto. Picking steel off a delivery trailer with a crawler crane therefore points to general liability, whose “loading or unloading” leaves out that movement too. Commercial auto is for tractors, trailers and pickups in traffic. Exclusion h takes hauling the crawler on your own lowboy out of general liability, so raise it on the auto quote.

The controlling entity must see that ground preparation is provided and tell you about buried hazards in documents it holds or otherwise known to it.

Rivers, railroads and old paint

Over water. In its 1983 Perini decision, on a construction worker hurt aboard a cargo barge at a plant being built over the Hudson, the U.S. Supreme Court, over one dissent, held only that a worker injured on actual navigable waters, in the course of employment there, is covered by the Longshore Act if the employer qualifies and no exclusion applies. It left open the worker who is on the water only transiently or by chance. The Act also takes in adjoining piers and areas customarily used in loading, unloading, repairing, dismantling or building a vessel, but the worker must also be engaged in maritime employment. Before setting bridge steel from a barge, ask for Longshore coverage on the compensation policy.

Beside track. Within 50 feet of railroad property, the “insured contract” definition leaves out indemnity to a railroad for construction affecting a bridge, trestle, track or crossing. Ask to have that limitation removed for the job.

Torch work on old steel. Where lead coatings are present, OSHA has the employer treat people welding, cutting or torch burning as exposed above 50 times the permissible limit until an assessment documents otherwise. Exclusion f reaches pollutants that you, or someone for you, handled or transported “as waste,” a paragraph with no exception of its own, so paint chips can start that argument. Ask about contractors pollution liability.

Where steel has its own license class

California’s Contractors State License Board separates C-51 structural steel from C-50 reinforcing steel and C-23 ornamental metal. Nevada’s C-14 license has subclassifications for structural steel, reinforcing steel, prefabricated steel structures, and rigging and cranes, among others. Virginia’s steel erection specialty includes rebar and post-tensioning. New Mexico’s GS-24 does not authorize concrete foundations or complete buildings.

South Carolina requires a license when the total cost of construction is greater than $10,000, with separate subclassifications for structural framing, miscellaneous metals and pre-engineered metal buildings, but a licensee may use unlicensed subcontractors within its own license if it supervises them.

Height, structure and what moves the premium

Compensation classes follow the structure. Florida’s construction rule, from a class list updated through January 1, 2011, names 5040 for steel frame structures, 5059 for frames not over two stories, 5069 for dwellings not over two stories and 5057 for erection not otherwise classified. Washington puts steel building frames in 0518 and sends bridges to 0201 and silos and towers to 0508.

General liability pricing starts from payroll or receipts by type of frame, maximum height, cranes and who directs picks, subcontracted work, states, tie-off policy and citations, design, and claims. A commercial umbrella should not bring back a height or employee-injury exclusion that the policy below it lacks.

Questions steel erectors ask

How much does steel erectors’ insurance cost?

It is priced from the facts in the section above; send them for a figure.

Who insures structural steel erectors on high-rise jobs?

An independent agent can ask the companies it represents. Bring the fall protection program, and read any height limit word for word.

Does a steel contractor need warehouse legal liability?

Only if you store property for others. If you hold a fabricator’s steel in your yard for a fee, ask for bailee or warehouse coverage, because j(4) applies there too.

Is a steel fabricator insured the same way as an erector?

No. A fabricator also needs product liability, and commercial property for the shop.

Ask for a steel erection quote

Send the job list with heights and contract values, payroll by structure, a sample subcontract, crane list, safety program, drivers and vehicles, licenses and loss runs. Wexford Insurance is an independent agency in Greenwood, Indiana, licensed in 48 states, with a focus on the construction industry. We compare coverage and price across the insurance companies we represent.

Start your quote or call 317-942-0549. Related pages: contractor insurance and business insurance.

Sources

Steel Erection Contractors: related pages

Steel Erection Contractor Insurance by state

Get A Free Quote

Call 317-942-0549 or request a quote online.

Get A Free Quote